Belvoir Street Theatre Refurbishment

Belvoir Street Theatre Refurbishment

Belvoir Street Theatre Refurbishment

Key insights:

  • Involved in ECI.
  • Aggressive 7 week around the clock construction program.
  • 50 Point in ground sewer drainage services & set out.
  • Setting and installing 20 metres of in ground stainless steel grated drains into polish concrete slab.
  • Supply of all fixtures and tapware consisting of 20 toilets, 25 basins, 5 urinals and 2 showers.
  • Hot & cold water supply designed to suit “Peak time” usage before and after shows.

Project Detail

Project
Belvoir Street Theatre Refurbishment
Client
Fugen Constructions
Scope:
Installation of services& fixtures for new ground floor amenities.